How long does planning take in London for a small scheme?

How long does planning take in London for a small scheme?

Check My Land7 October 2026·2 min read
Share:

Anyone planning to sell or develop a London plot wants to know how long the planning process takes. We measured it across the small housing schemes, one to nine homes, that London councils decided from January 2021.

The London picture

The median time from a valid application to a decision is 92 days, about 13 weeks. The statutory target for this kind of application is 8 weeks, or 56 days, so the typical scheme runs a month past it, often because applicant and council agree an extension while the design is amended.

The fastest boroughs

  • Barking and Dagenham: 57 days
  • Barnet: 69 days
  • Brent: 72 days
  • Ealing: 76 days
  • Enfield: 77 days
  • Redbridge: 83 days
  • Lewisham: 86 days
  • Havering: 86 days

The slowest boroughs

Among boroughs with at least 100 decisions:

  • Camden: 329 days
  • Richmond upon Thames: 191 days
  • Hackney: 190 days
  • Southwark: 160 days
  • Islington: 127 days

Camden stands out. The median small scheme there takes nearly a year from application to decision.

Fast is not the same as yes

Speed and approval do not travel together. Barking and Dagenham decides quickly and approves 37 per cent. Camden decides slowly and approves 62 per cent. Ealing and Enfield are both fast and approve 59 per cent each, which is the combination worth looking for.

What the clock does not include

These figures start at the date a valid application is received. They do not include the time before: the survey, the design, the pre-application meeting with the council if you have one, and the weeks it can take for an application to be validated. A realistic timeline from first sketch to decision notice in most of London is six months at the quick end and well over a year in the slow boroughs.

What to do with it

If you are thinking of selling to a developer, ask how long they expect planning to take in your borough and who carries the cost of waiting. In an option agreement the developer pays for the planning application and takes the time risk, which is a large part of why landowners choose that route. We explain how it works in option agreements explained.

Check your land, free

Figures: 11,369 decided planning applications since 1 January 2021 where the applicant's form declared one to nine net new homes, from the councils' own registers; medians of days from received to decided. Tower Hamlets, Newham, Wandsworth and Haringey are not yet in our data.

Own land somewhere in particular? The Land by postcode pages show recent sales, planning designations and the deciding council for each district.

More articles

Check your land for free

Find out which constraints affect your property and what your options are. Takes two minutes.

Check my land →